Bab traffic light kat KHTP ni kalau sapa dok selalu guna jln tu pi kerja, mungkin akan terasa. Tapi yg sekali sekala guna tu kata biasa saja.
Aku heran….., masalah ni dah dibangkitkan sejak bulan Julai 2009 tapi proses menunding jari ni meleret hingga Februari 2010 sehingga Hj Sobri bagi arahan kat staf dia “Please take necessary action”.
Kalau tak silap aku….. sampai la masih lagi tergantung status dia sebab aku balik baru2 ni tengok tak ada perubahan pun.
Kita layan pi ajalah email bawah ni…..:
From: Patrick Teh [mailto:patrick@KHTP.COM.MY] Sent: Thursday, July 16, 2009 11:51 AM To: Amran, Md; Chai Cc: Huinee_Auyong@sngw.els.hoya.co.jp Subject: Traffic Lights Timings at BKE & First Solar Junctions Importance: High Dear Amran and Chai, This is what I have personally observed on-site today at 9.30am for the following junctions that have caused some concerns to employees in KHTP: A. BKE 1. From Lunas Toll on BKE towards KHTP at Paya Besar junction: 45 seconds (green) 2. BKE/Sg Seluang (Padang Serai) junction: 45 seconds (green) 3. The per-loop timing (green to green) observed at #1 junction was 120 seconds. Notes: a. The green light at the Sg Seluang junction was a bit delayed after the Paya Besar junction has turned green. b. At 8am today: Junction #1 was 45 seconds and Junction #2 was about 57 seconds. c. BKE promises to look into adding more time for both junctions by next week. B. Lebuhraya Perdana/First Solar Junction towards KHTP Business Centre 1. Green light timed at 18 seconds. 2. Per-loop (green to green) was timed at 88 seconds Notes: a. KTPC is still the owner of this traffic light junction, pending surrender to PBT. b. KTPC will retime the lights because, on paper, according to our Development Division. the particular green light is supposed to be on for 60 seconds. Hope the above explains the issues that was brought up by KITA employees. (tak payah kata la issue ni mai drp sapa, KHTP sepatutnya jaga nama baik tu.....) But please keep the feedback coming and we will strive to correct any shortcomings to our tenants' satisfaction in the fastest way and time possible. (sampai la.....) Thanks and happy working, Patrick |
From: Amran, Md Sent: Thursday, July 16, 2009 1:30 PM To: Patrick Teh; Lim, LK; Sow, Yeek Kooi; Low, OS Cc: Chai Subject: RE: Traffic Lights Timings at BKE & First Solar Junctions Thanks Patrick, I am forwarding this to some of the Intel managers who are the regular users of the route, and they also have some subordinates who use the route frequently and gave feedback on the issue. (Amran..... Nasib baik hang sebut Manager yg complain, kalu tak mampus dia nak layan..... Itupun lama mana depa ambil masa nak selesaikan.....?) OS, YK, LK, Patrick Teh, who is the KTPC PR Manager has graciously stepped in to help with the traffic lights issues at the two junctions after BKE toll as well as the First Solar junction. Thanks and regards, Amran bin Mohamad Dom | Government Affairs Manager | Intel Malaysia M +6012 470 xxxx O +604 433 xxxx |
From: Sow, Yeek Kooi [mailto:yeek.kooi.sow@intel.com] Sent: Friday, 17 July, 2009 4:56 AM To: Low, OS; Amran, Md; Patrick Teh; Lim, LK Cc: Chai Subject: RE: Traffic Lights Timings at BKE & First Solar Junctions Thank you Patrick. As long as we have a process to listen and receive feedback, I am sure we could continue making KHTP a better investment place. One simple process that we have in PG and some other places across Msia is having the handphone Contact No stick to each traffic light. In this way, we know who to contact when traffic light malfunction. We need to ensure those people working on the ground and those define the requirement always place themselves at the user of point of view. (YK..... who are u to say so..... mana ada KHTP buat pun..... Unless your good suggestion come from LK or other Big BOSS). Thanks. yk sow/Intel |
From: Patrick Teh [mailto:patrick@KHTP.COM.MY] Sent: Tuesday, July 28, 2009 1:12 PM To: Sow, Yeek Kooi; Low, OS; Amran, Md; Lim, LK Cc: Chai Subject: RE: Traffic Lights Timings at BKE & First Solar Junctions Dear All, I have some updates on the traffic lights in KHTP and BKE: 1. BKE/Paya Besar/Sg Seluang: BKE has retimed the lights at this junction to 60 seconds for both the lights at BKE/Paya Besar and BKE/Sg Seluang junctions leading to KHTP. The timing loop from green-green is now 180 seconds. Please let me know if these retimings are OK. 2. For the Lebuhraya Perdana-First Solar junction, this will hopefully be done soonest pending the availability of the technician responsible. KTPC will follow up on this. 3. For the Lebuhraya Perdana-Jalan Hi-Tech 1 junction, I have personally spoken to the Kulim District JKR Engineer last week who promised to speak to their Electrical section regarding the traffic light timings, etc at this junction. (Ya ka hang cakap personally.....?) Thanks and regards |
From: "Sow, Yeek Kooi" <yeek.kooi.sow@intel.com> To: Patrick Teh <patrick@KHTP.COM.MY>, "Low, OS" <os.low@intel.com>, "Amran, Md" <md.amran@intel.com>, "Lim, LK" <lk.lim@intel.com> Cc: Chai <eng_leng_chai@entegris.com> Date: 08/17/2009 02:03 PM Subject: RE: Traffic Lights Timings at BKE & First Solar Junctions Hi Patrick - I am sorry to trouble you again. Since last week and including this morning, the 2 BKE traffic lights after Lunas toll were back to their old problem again. Both lights timing is out (1st at ~50 secs, 2nd at ~40 secs) and both are not synchronized. When the 1st light from toll is Green, the 2nd one is RED. This caused long jam from the toll. The same problem on both lights when we entered BKE from KHTP. I am sure all of us were frustrated on why we cannot fix this simple problem despites tenths of feedback. If the traffic light controller is not capable, change it, if the people that manage this not capable, replace them. .... or we don't call it "High Tech Park" anymore for not able to manage a low tech problem. (Change all the HJ's there then everything will change). We just need a permanent solution. AND we need who ever is accountable to have a process to monitor and trigger by themselves. Thanks for you help again. Thxs..yk |
-----Original Message----- From: eng_leng_chai@entegris.com [mailto:eng_leng_chai@entegris.com] Sent: Monday, 17 August, 2009 2:57 PM To: Sow, Yeek Kooi Cc: Lim, LK; Amran, Md; Low, OS; Patrick Teh Subject: RE: Traffic Lights Timings at BKE & First Solar Junctions YK, I can sense some frustration from your email. Entegris invited the Kedah Road Safety Department (JKJR) Director to give a road safety awareness talk. I spoke to him briefly after the talk about some road accidents within the park, and about how the traffic lights and U-turns could be better managed. He asked that if there is any concerns that are still open and that we are not getting the right response, we can write in to him. (Pengilang juga cari inisatif utk cuba selesaikan masalah) So here is his details: Surentharan A/L Mathavan, Director cum Secretary of MKJR Kedah email: surentharan_kdh@jkjr.gov.my HP: 0125339378 Perhaps we can try to route the issue to get some attention and see if the Director of JKJR will indeed help resolve them. Best Regards EL Chai | Plant Manager, Global Supply Chain Entegris (Malaysia) Sdn Bhd | Lot 17, Phase 1 Kulim Hi-Tech Park | Kulim, Kedah 09000 Malaysia | Tel. +604 427-4201 | Cell +6012 431-9803 | www.entegris.com The materials integrity management company |
-----Original Message----- From: Patrick Teh [mailto:patrick@KHTP.COM.MY] Sent: Monday, August 17, 2009 4:25 PM To: eng_leng_chai@entegris.com; Sow, Yeek Kooi Cc: Lim, LK; Amran, Md; Low, OS; rozamin@pbttphtk.gov.my Subject: RE: Traffic Lights Timings at BKE & First Solar Junctions YK, as a road user of the same stretch and junction, I am as fed up as yourself. So, I can empathise with you. In fact this morning, I've informed Hj Mohd Asri of BKE about it again after doing likewise the previous week for similar out-of-sync occurrence. I am copying this email to seek the assistance of En Rozamin of PBT KHTP to help in following up with BKE regarding the issue. (Follow up Hj Patrik oiiiii..... hang sendiri cakap " Thanks. |
-----Original Message----- From: Sow, Yeek Kooi Sent: Monday, August 17, 2009 4:56 PM To: Patrick Teh; eng_leng_chai@entegris.com Cc: Lim, LK; Amran, Md; Low, OS; rozamin@pbttphtk.gov.my Subject: RE: Traffic Lights Timings at BKE & First Solar Junctions Hi All - thank you very much for your attention. I hope we can come together to get this fix and make KHTP a great place to invest and to work in Kulim. Thanks. Yk |
From: "Lim, LK" <lk.lim@intel.com> To: "Sow, Yeek Kooi" <yeek.kooi.sow@intel.com>, Patrick Teh <patrick@KHTP.COM.MY>, "eng_leng_chai@entegris.com <eng_leng_chai@entegris.com> Cc: "Amran, Md" <md.amran@intel.com>, "Low, OS" <os.low@intel.com>, "rozamin@pbttphtk.gov.my" <rozamin@pbttphtk.gov.my> Date: 08/18/2009 07:58 AM Subject: RE: Traffic Lights Timings at BKE & First Solar Junctions I do agree with YK. In fact many of us have been working here since KHTP startup way back in 1996 but sadly to say till today still experiencing infrastructure problem like traffic light timing setting. This issue has become even more pressing now with the rapid growth in KHTP. We surely need fast action from authority to rectify those issues and the best is put a permanent fix solutions. Besides, the authority should also look into constant monitoring and effectiveness in sustaining the system. Regards, LK Lim |
-----Original Message----- From: Low, OS [mailto:os.low@intel.com] Sent: Wednesday, 18 November, 2009 8:49 AM To: eng_leng_chai@entegris.com; Lim, LK; Muhamad Sobri Osman Cc: Amran, Md; Patrick Teh; Sow, Yeek Kooi Subject: RE: Traffic Lights Timings at BKE & First Solar Junctions Traffic timings is still in an unacceptable state during peak hours inspite of many feedbacks - the 2 traffic lights after BKE and also the traffic lights turning into the KHTP. This is impacting workers productivity at the Park. I suggest if this cannot be resolved, we need to get it escalated to the Ministry and get this fixed permanently once and for all. Not a very good impression to investors if this simple issue cannot be resolved in an expedient manner. A last point - we should review the condition of all traffic lights in the park (there are still some at the park having similar timing issues causing traffic back-up in the evening peak hrs) and we should look at using sensor trigger traffic lights instead of time control. Thanks and Hope this can be addressed quickly. Rgds-os |
-----Original Message----- From: Patrick Teh [mailto:patrick@KHTP.COM.MY] Sent: Wednesday, November 18, 2009 9:38 AM To: Low, OS; eng_leng_chai@entegris.com; Lim, LK; Muhamad Sobri Osman Cc: Amran, Md; Sow, Yeek Kooi; Khairul Fithri Osman; rozamin@pbttphtk.gov.my Subject: RE: Traffic Lights Timings at BKE & First Solar Junctions Agreed. I have brought this matter to my colleague, Fithri (Dep. VP - Development, who would get the right people to rectify the situation immediately. The Lebuhraya Perdana traffic volume was exceptionally high because of the traffic police who was allowing more cars than usual to enter Lebuhraya Perdana during any given time. (Hang dgn Fithri sama saja..... Tambah Fithri senyap terussssss.....) I would think that the best solution is for KTPC (the owner of the traffic lights at First Solar junction until we hand over to PBT) and JKR to sit down to synchronise, optimise and monitor the lights from time to time so that situations like these can be kept to a minimum. I will await Fithri's advice on the above. Thanks for the feedback. Regards, Patrick |
-----Original Message----- From: Sow, Yeek Kooi [mailto:yeek.kooi.sow@intel.com] Sent: Wednesday, 18 November, 2009 2:29 PM To: Patrick Teh; Low, OS; eng_leng_chai@entegris.com; Lim, LK; Muhamad Sobri Osman Cc: Amran, Md; Khairul Fithri Osman; rozamin@pbttphtk.gov.my Subject: RE: Traffic Lights Timings at BKE & First Solar Junctions Hi Patrick/all - thank you for your help AGAIN! We have feedback this 19 times and the problem seem to repeat over and over again. We are more than happy to participate in solving this problem if we could be at help...of giving the right inputs and how the traffic lights could be set from user point of view. Thanks. yk / Intel |
-----Original Message----- From: Patrick Teh [mailto:patrick@KHTP.COM.MY] Sent: Wednesday, November 18, 2009 2:57 PM To: Sow, Yeek Kooi; Low, OS; eng_leng_chai@entegris.com; Lim, LK; Muhamad Sobri Osman Cc: Amran, Md; Khairul Fithri Osman; rozamin@pbttphtk.gov.my Subject: RE: Traffic Lights Timings at BKE & First Solar Junctions YK, Why not? I'll find the appropriate date, time and venue and let's make it work once and for all, for all! (Apa yg hang merepet ni.....? Apa VP Development buat.....?) Thanks again. Patrick |
-----Original Message----- From: "Sow, Yeek Kooi" yeek.kooi.sow@intel.com Date: Wed, 10 Feb 2010 06:32:38 To: Patrick Teh<patrick@KHTP.COM.MY>; eng_leng_chai@entegris.com <eng_leng_chai@entegris.com>; Muhamad Sobri Osman <sobri@KHTP.COM.MY> Cc: Amran, Md <md.amran@intel.com>; Khairul Fithri Osman<fithri@KHTP.COM.MY>; rozamin@pbttphtk.gov.my <rozamin@pbttphtk.gov.my>; Sow, Yeek Kooi <yeek.kooi.sow@intel.com> Subject: Traffic Lights Timings at BKE & First Solar Junctions Hi Hj Sobri / Patrick I do want to follow-up on the traffic light discussion we had during NCIA meeting. In recent weeks, both the traffic lights at BKE/Lunas toll and First solar are out of control again causing huge jam, and resulted in employees late from attending biz meeting, and late from going home. We really need immediate attention and get this address. This is extremely sad that we can't even resolve a simple traffic light setting issue in our High Tech Park. Please let me know if I can be at help to talk to the right party on what is needed to resolve this issue. Thanks. yk sow/Intel-KITA |
FYI Thank you and best regards, Ku Rizal -----Original Message----- From: Muhamad Sobri Osman Sent: Wednesday, February 10, 2010 8:19 AM To: Noor Izam Ishak; Ku Masharizal Ku Mahmood; Khairul Fithri Osman Subject: Fw: Traffic Lights Timings at BKE & First Solar Junctions Please take necessary action (Ni saja feedback dari Sobri.....?) Sent from my BlackBerry® wireless device via Vodafone-Celcom Mobile. |
Kesian kat Hj Sobri….., masalah traffic light pun dia tak dapat nak selesaikan dgn cepat. Last2 transfer kat staff jugak utk diselesaikan.
Lambat ambil tindakan macam ni yg buat pelabur malas nak masuk KHTP. Pelabur yg sedia ada cukup tak puas hati dgn perkhidmatan yg KHTP berikan.